Fact Pattern

On April 1, Nadia Okafor, owner of Hearthstone Bakehouse LLC ('Hearthstone'), a retail and wholesale bakery in the town of Alderwood, signed a written contract with Summit Kitchen Equipment Co. ('Summit'), a merchant manufacturer and dealer of commercial bakery machinery. Under the contract, Summit agreed to manufacture and deliver two custom heavy-duty commercial dough mixers (Model M-400) for a total price of $40,000 ($20,000 each), with delivery due on June 1. Hearthstone paid an $8,000 deposit at signing and agreed to pay the $32,000 balance upon delivery.

The signed written contract included a typed specification near the top: 'Each mixer includes a reinforced planetary gearbox guaranteed to handle 150-pound high-hydration dough batches.' In bold capital letters on the front signature page, the contract also stated: 'ALL GOODS SOLD AS IS.' Nothing in the contract mentioned warranty of title.

On May 10, Summit's sales manager emailed Nadia that factory steel delays prevented delivery on June 1 and asked whether Hearthstone would accept delivery on June 15 instead. Hoping to avoid finding a replacement supplier, Nadia replied by email: 'We can live with June 15 as a one-time courtesy, provided you confirm both mixers will arrive in time for our wholesale launch.' Neither party signed a formal amendment, and Summit gave no consideration for the extra two weeks. On May 15, Crestline Foods ('Crestline'), a regional grocery chain, notified Hearthstone that Crestline was moving its wholesale launch up to June 5 and would cancel its launch order unless Hearthstone had full mixer capacity by June 5. On May 16—before Summit had shipped the mixers, paid overtime freight, or changed its production schedule—Nadia emailed Summit: 'Our grocery launch moved up to June 5; we are retracting our courtesy extension and require delivery on the original June 1 contract date.'

On May 20, Summit replied in writing: 'We reject your retraction, and because our raw steel costs jumped 15 percent last month, we will not deliver on June 1 or June 15 unless you agree to pay $46,000 total instead of $40,000.' On May 22, Hearthstone sent Summit a formal written demand for adequate assurance under Uniform Commercial Code Section 2-609, requesting written confirmation within five days (given the imminent June 1 deadline) that Summit would deliver at the $40,000 contract price. Summit ignored the demand for six days and then emailed on May 28 refusing to deliver for less than $46,000.

On May 29, Hearthstone canceled the Summit contract and promptly purchased two comparable replacement mixers in good faith from Ironwood Machinery for $47,000 total ($7,000 above the $40,000 contract price), plus $600 in expedited freight charges, while saving $200 in local rigging fees that Hearthstone would have paid under Summit's delivery terms. Ironwood delivered the mixers on June 3, so Hearthstone missed Crestline's June 5 launch and lost $5,000 in documented net profit on the Crestline order. Summit had never been told at the April 1 signing about Crestline Foods or any June launch deadline. Nadia comes to your law office for advice on warranties, waiver and repudiation, recoverable damages, and drafting a pre-suit demand letter and file note.

Checked: 0 of 3 · Score: 0 / 3

Question 1 of 5 Select One of Four

Counseling — Express Warranty, Warranty of Title & 'As Is' Disclaimer

During the intake conference, Nadia points to the bold 'ALL GOODS SOLD AS IS' clause on the April 1 contract and asks whether that language would have wiped out Summit's promise about the 150-pound planetary gearbox as well as Summit's implied warranties and warranty of title if the mixers had been delivered. Which legal advice is MOST accurate? (Select one.)

Select one option.

Question 2 of 5 Select Two of Six

Counseling — Retraction of Waiver (UCC Section 2-209) & Adequate Assurance (UCC Section 2-609)

Nadia asks whether her May 10 email permanently locked Hearthstone into a June 15 delivery date, and whether Summit was entitled to 30 full days to answer Hearthstone's May 22 assurance letter. Which TWO legal points should you explain to Nadia? (Select two.)

Select two options.

Question 3 of 5 Select One of Four

Counseling — Buyer Cover Damages & Hadley Foreseeability (UCC Sections 2-711, 2-712, and 2-715)

Nadia asks for the exact dollar amount Hearthstone can recover from Summit under UCC Article 2, including whether Hearthstone can recover the $5,000 lost profit from Crestline Foods' canceled launch order. Which calculation and legal explanation is MOST accurate? (Select one.)

Select one option.

Question 4 of 5 Short Written Response

Counseling — Commercial Impracticability & Good-Faith Modification

Nadia tells you Summit's sales manager insisted that the 15 percent steel price spike excused Summit from delivering at $40,000 and that UCC Article 2 lets a seller raise the price without new consideration. Draft a concise 3-to-5 sentence counseling explanation advising Nadia why both of Summit's arguments fail.

Question 5 of 5 Short Written Response

Drafting — Demand Letter Paragraph & Internal Damages/Deposit Note

You are preparing a pre-suit demand letter to Summit and an internal memorandum note for your supervising partner. Draft: (a) two to three sentences for the demand letter explaining Summit's anticipatory repudiation and demanding the exact $15,400 recovery under Uniform Commercial Code Article 2; and (b) two to three sentences for the internal file note explaining whether Summit could have recovered consequential damages if Hearthstone had been the breaching buyer, and how Uniform Commercial Code Section 2-718(2) would treat a breaching buyer's $8,000 deposit refund claim in the absence of a liquidated-damages clause.